South Kingstown Public Schools
Recommended Capital Improvement Plan
Period Beginning July 1, 2008
Six-Year Bonded Component
FY 2009 through FY 2014
This document details the projects proposed by the school department for completion during the next six year period. It is based on the facility audit completed in July 2001. This yearÕs submission includes changes from prior plans based on a reapplication of the facility study in accordance with current conditions. The following priorities guided the development of this document:
In order to address these priorities, the following systems were reviewed:
There are additionally changes in the presentation and organization of the capital plan this year. The most significant, although not only, factor creating the changes is the reduction in available revenue resulting from a combination of the local property tax cap and restrictions in state aid. Notable among these changes are:
District-wide
6-year plan
Roof Replacement
Roofs are scheduled for replacement on a 20-year schedule. All flat roofs will be replaced with built up modified bitumen roofs. This design is vandal resistant, provides added protection from the weather and the life expectancy is much greater than the single ply. Actual life of roofs can vary, and the actual time of replacement can be adjusted as the scheduled time approaches depending on roof condition. All current roofs are in good condition or better and there are none in need of immediate replacement. Shown below are roofs scheduled for replacement and their installation date.
|
Roofing Summary |
|
|
|
|
|
|
Roof |
Installation |
FY2009 |
FY2011 |
FY2013 |
Total Program |
|
High School Addition |
1993 |
|
|
765,000 |
765,000 |
|
West Kingston Additions |
1987, 1991 |
|
275,000 |
|
275,000 |
|
Wakefield Addition |
1990 |
|
75,000 |
|
75,000 |
|
Matunuck Additions |
1987, 1991 |
|
275,000 |
|
275,000 |
|
Total Annual |
|
|
625,000 |
765,000 |
1,390,000 |
|
|
|
|
|
|
|
Flooring Replacement
This replaces worn out flooring throughout the district, including carpets and VAT (vinyl asbestos tile). Included in this project is the necessary asbestos abatement work and moisture sealant where necessary. All flooring will be replaced with VCT or a hybrid that is a cross between tile and carpet (fuzzy tile). The application will be determined by the location and use of the area. The hybrid tile product is solid backed and seals out moisture and dirt from penetration. This product carries a 20 year guarantee. This work will improve indoor air quality and avoid potential allergic reactions.
|
Floor
Replacement |
|
|
|
||||
|
School
Facility |
FY 2009 |
FY 2011 |
FY 2013 |
Total Program |
|||
|
High
School |
|
20,000 |
|
20,000 |
|||
|
Curtis
Corner |
|
80,000 |
|
80,000 |
|||
|
Peace
Dale |
50,000 |
|
|
50,000 |
|||
|
West
Kingston |
|
|
275,000 |
275,000 |
|||
|
Wakefield |
30,000 |
|
|
30,000 |
|||
|
Matunuck |
|
|
275,000 |
275,000 |
|||
|
Administration |
|
30,000 |
|
30,000 |
|||
|
Total
Annual |
80,000 |
130,000 |
550,000 |
760,000 |
|||
|
|
|
|
|
|
|||
Lighting Upgrades
The schools have been successful in saving costs through energy conservation. To date, savings have come through changes in behavior. Additional savings will require some capital investment, the most pressing through energy efficient lighting fixtures and switching. RISE completed an audit of several schoolsÕ fixtures to establish priorities and retrofits were prioritized by the audit results. In 2007-08 facilities with the highest reimbursement (PDES, WES, CCMS, Hazard, and Administration at 75%) were retrofitted with an expected 2-year payback. The next priority is schools with a lower reimbursement due to utilization (SKHS, MES, and WKES). These carry only a 25% reimbursement and are scheduled for 2008-2009. An audit is complete for the high school (see below) and is awaited for Matunuck and West Kingston. The elementary school data reflects an estimate from National Grid and RISE Engineering. The plan is to do one-third of the high school next year, the elementary schools in 09-10, and finish the high school in 10-11. Upon completion of the full audit this data will be updated. To utilize energy savings to repay project costs, a line will be established in the operations budget to transfer to the town an amount to meet the bonding obligation.
|
Proposed
Lighting Upgrade |
|||||||
|
|
Year |
Cost |
Incentive |
Net Cost |
Savings kW |
Savings $ |
Payback |
|
SKHS |
2009 |
$261,223 |
$62,030 |
$199,193 |
233,182 |
$45,607 |
4.4 years |
|
MES |
2010 |
$22,400 |
$5,600 |
$16,800 |
|
|
|
|
WKES |
2010 |
$22,400 |
$5,600 |
$16,800 |
|
|
|
WKES and MES Electric Systems
The electrical systems at Matunuck and West Kingston are currently functional and functioning. These are both electrically heated schools, so have heavy loads, especially in winter. The major issue is that their control systems are obsolete and no longer manufactured. Replacement parts are currently available from suppliers, but inventory is not replenished. Consequently, a time will come when the systems cannot be repaired and extensive work may be necessary. Similarly, with these schools conversion to a heating system that is not electric has been considered. However, with current energy pricing, a conversion is not cost beneficial and consequently not planned. This should be monitored, however.
FY 2009
Projects - $463,000
High School
Hazard Field Renovation ($150,000) - Funds are allocated to grade, add topsoil, reseed, install irrigation, and replace fencing in order to maintain and improve the field for heavy usage. The Hazard field has minimal topsoil and, consequently, a weak grass cover. It is a hard field with rocks, increasing risk of injury. Additionally, over the years usage has grown (girlÕs teams and lacrosse in the spring) leaving the field with no recovery time. If we have a dry summer the practices leave the area with little or no ground cover. Community groups stopped using the field years ago because of the situation. Additionally, many of our physical education classes use Old Mountain field because of the condition of Hazard field. This is a practice that takes away from valuable class time and is a safety issue when crossing Route 108. We have had two students hit by cars and other close calls. After consulting with town recreation, we believe that with proper irrigation and field maintenance Hazard Field can become a safer and more versatile playing area for the schools and the town for decades to come. It will also make school time more efficient by reducing the need to walk classes to Old Mountain Field. The final result will be an overall safer program with greater field availability.
Peace Dale School
Replace Flooring ($50,000) - This will replace the flooring on the upper floor of the building.
Wakefield School
Replace Flooring ($30,000) - This will replace the flooring in the addition to the building.
Lighting Upgrades
SKHS, MES, and WKES ($233,000) - The next priority is schools with a lower reimbursement due to utilization. These carry 25% reimbursement with a payback of between 4 and 5 years and are scheduled for 2008-2009.
FY 2011
Projects - $1,005,000
High School
Replace Flooring ($20,000) - This will replace the flooring in the library.
Curtis Corner Middle School
Replace Flooring ($80,000) - This project replaces the VAT flooring in the 100, 200 and 300 wings of the building.
Administration
Replace Flooring ($30,000) - This project will replace the original carpeting in the administration building.
West Kingston School
Roof Replacement ($275,000) - This will replace the roofs on the original and second additions to the school.
Matunuck School
Roof Replacement ($275,000) - This will replace the roofs on the original and second additions to the school.
Wakefield School
Roof Replacement ($75,000) - This project will replace the original roof on the addition to the school.
Replace Single Pane Windows ($250,000) - This will replace the single pane windows installed in the original building.
FY 2013
Projects - $1,655,000
High School
Roofing ($765,000) - This project will replace the roofs on the buildingÕs additions.
Curtis Corner Middle School
Replace HVAC System ($400,000) - This will replace the original HVAC units on the 400 wing of the building with energy efficient gas fired units that are digitally controlled for maximum energy savings, expand air conditioning to areas of the building occupied year-round, and replace unit ventilators in the original building.
Administration
Replace Rooftop AC Units ($90,000) - This will replace the original HVAC units with digitally controlled gas fired units for maximum energy efficiency.
West Kingston School
Replace Flooring ($200,000) - This project will replace flooring in the entry, corridors and other remaining isolated spaces. It completes the replacement program.
Matunuck School
Replace Flooring ($200,000) - This project will replace flooring in the entry, corridors and other remaining isolated spaces. It completes the replacement program.
|
|
|
|
|
|
|
|
|
Facility |
Fiscal Year 2008 |
Fiscal Year 2009 |
Fiscal Year 2011 |
Fiscal Year 2013 |
Six
Year Total |
|
|
|
|
|
|
|
|
|
|
High School |
|
|
|
|
|
|
|
Replace flooring |
0 |
$
- |
$ 20,000 |
|
$ 20,000 |
|
|
General Renovations |
705,000 |
$
- |
$
- |
$
- |
$
- |
|
|
Roofing |
0 |
$
- |
$
- |
$
765,000 |
$ 765,000 |
|
|
Hazard Field Renovation |
0 |
$ 150,000 |
$
- |
$
- |
$ 150,000 |
|
|
Subtotal |
$ 705,000 |
$ 150,000 |
$ 20,000 |
$ 765,000 |
$ 935,000 |
|
|
|
|
|
|
|
|
|
|
Curtis Corner Middle
School |
|
|
|
|
|
|
|
Unit heaters and cabinet
ventilators |
$
- |
$
- |
$
- |
$
400,000 |
$ 400,000 |
|
|
Renovation |
$
- |
$
- |
$
- |
$
- |
$
- |
|
|
Replace flooring |
$
- |
$
- |
$ 80,000 |
$
- |
$ 80,000 |
|
|
Replace rooftop air
conditioning units |
$
- |
$
- |
$
- |
$
- |
$
- |
|
|
Subtotal |
$ - |
$
- |
$ 80,000 |
|||